Storm Damaged Dock Repair in Miami
Storm damaged dock repair in Miami has a federal clock on it. Under the Army Corps maintenance permit, work has to start, or be under contract, within two years of the damage.
Nationwide Permit 3, as written
The Corps reissued its nationwide permits in the Federal Register on January 8, 2026. They took effect March 15, 2026. Number 3 is maintenance:
(a) The repair, rehabilitation, or replacement of any previously authorized, currently serviceable structure or fill, or of any currently serviceable structure or fill authorized by 33 CFR 330.3, provided that the structure or fill is not to be put to uses differing from those uses specified or contemplated for it in the original permit or the most recently authorized modification. Minor deviations in the structure's configuration or filled area, including those due to changes in materials, construction techniques, requirements of other regulatory agencies, or current construction codes or safety standards that are necessary to make the repair, rehabilitation, or replacement are authorized. This NWP also authorizes the removal of previously authorized structures or fills. Any stream channel modification is limited to the minimum necessary for the repair, rehabilitation, or replacement of the structure or fill; such modifications, including the removal of material from the stream channel, must be immediately adjacent to the project. This NWP also authorizes the removal of accumulated sediment and debris within, and in the immediate vicinity of, the structure or fill. This NWP also authorizes the repair, rehabilitation, or replacement of those structures or fills destroyed or damaged by storms, floods, fire or other discrete events, provided the repair, rehabilitation, or replacement is commenced, or is under contract to commence, within two years of the date of their destruction or damage. In cases of catastrophic events, such as hurricanes or tornadoes, this two-year limit may be waived by the district engineer, provided the permittee can demonstrate funding, contract, or other similar delays.
Notice "previously authorized." It points back to the original permit. Do you have yours? Find it now, before you need it.
Pulling out what's left
A rotting pile or a dock that's falling apart can come out without a Class I permit. From the county's exempt list:
The following is a list of projects that are exempt from a Class I Permit.
- (g) The removal of old or unused or rotting piles or the removal of dilapidated docks, boatlifts, davits, or piers.
Inside City of Miami limits
The city's post-storm plan lists these under work that needs a permit, heading Structural Permits:
- Demolition (partial or full)
- Load-bearing element repairs
- Structural framing repairs
- Wall reconstruction
- Wood deck repairs
IMPORTANT: If you are unsure whether a permit is required, please consult the Building Department.
Docks aren't named there. Decks are. Take photos before anything gets hauled off, then send us the address. Piles hit hardest? See dock piling repair.